Every empty office tower gets pitched as future housing before anyone checks whether the building can physically become housing.

It's an appealing story, and the appeal is showing up in the numbers. Roughly 90,300 office-to-apartment conversions are projected for 2026, a 28% jump from the prior year and close to four times the volume seen in 2021. Downtowns have too much vacant office space and not enough housing, and converting one into the other looks like it solves both problems at once. Makes sense, right? However, there are very real constraints.

Let’s Get Physical

Office buildings were built for a specific kind of floor plate: deep, open, lit by fluorescent tubes and cooled by centralized HVAC systems. A typical office floor works fine with people sitting 35 to 40 feet from the nearest window, because artificial light and mechanical ventilation carry the space. However, residential building codes doesn't allow that. Every habitable room, bedroom or living room, to have a window equal to at least 8% of the floor area. A deep floor plate that made sense for a trading floor creates a dead zone in the middle of a residential layout: space too far from any exterior wall to legally become a bedroom. That space doesn't disappear when you convert the building. It just stops generating revenue.

Floor plate depth should be a primary focus. And the math is more specific than most people assume. A building around 50 to 60 feet deep can put nearly all of its square footage within reach of a window, which makes it an excellent to good candidate. At 70 feet, a typical office depth, usable residential area drops to around 86%. At 80 feet it falls to roughly 75%. At 100 feet, usable area drops to around 60%, and at that depth a conversion usually doesn't work without cutting light wells into the structure. Once a building loses a quarter of its floor area to dead space, the cost per usable square foot climbs to match or exceed new construction, which runs $500 to $600 per square foot in many markets, and the economic case for reuse disappears.

There's another problem that gets less attention than floor plates but matters just as much: plumbing. Office buildings are built around centralized, concentrated plumbing cores serving communal restrooms on each floor. Residential buildings need plumbing distributed to every single unit, floor by floor, apartment by apartment. Cutting through reinforced concrete to run new waste lines typically runs $40 to $80 per square foot. Some developers route around that cost with above-floor pump systems, sometimes called macerating pumps, that push waste up to existing drain lines instead of cutting down through the slab. It avoids the concrete bill, but it adds mechanical complexity, maintenance burden, and noise that shows up later, in the finished unit, not in the underwriting.

Lastly, and the most critical question to ask is can the building structurally support the added floor load that’s created because of the conversion. Recently, a massive office-to-residential conversion at the former Pfizer headquarters in Midtown Manhattan into 1,600 apartments experienced a near-collapse caused by buckled structural steel columns on the 21st floor. The incident triggered a citywide safety crackdown on similar conversion projects by the New York City Department of Buildings, resulting in immediate inspections and work stoppages at other sites.

So Do Conversions Make Sense?

Admittedly, AI is changing how fast owners and investors can screen for all of this. A traditional feasibility study can take three to six months and cost upward of $100,000. Tools like Gensler's Conversion Score and Autodesk's X-Ray Vision, built with Arcadis, compress that into a screening that runs in about 30 seconds, inferring core placement and structural viability from legacy plans and building data. That's a real efficiency gain. But it creates its own risk: if every lender and developer is running the same handful of tools against the same national office stock, everyone converges on the same small pool of genuinely viable buildings at the same time, and the discount that made those deals attractive starts compressing fast.

Even the buildings that clear these tests usually aren't converted to residential. In Atlanta, a building at 50% vacancy still needs roughly $46 per square foot in new grant funding to close the remaining gap. Other cities have built the subsidy into policy directly: Calgary offers grants up to $56 per square foot, and Boston offers a 75% property tax abatement for up to 29 years.

Which leaves the harder question nobody wants to sit with: what happens to the buildings that fail these tests? By some estimates, roughly 70% of the existing office stock is architecturally stranded, physically unable to become legal, livable housing under current codes. As one architect involved in several feasibility reviews put it, no amount of tax incentive or adaptive reuse ordinance can solve for the physical constraints of a building. That's the actual scale of this problem. Converting the buildings that work is the easy headline. Deciding what happens to the majority that never will is the real challenge downtowns are going to have to face.